Drivers have been warned that three months of disruptions will be in play on the M4 as bridge repairs take place in Reading.

Disruptions will occur between 9pm and 6am throughout April, May, June and July between Junction 11 Reading and Junction 12 at Theale.

National Highways will be carrying out repairs on the Burghfield Road Bridge including replacing the existing paint system and refurbishing the bridge bearings, to ensure it remains in a safe condition. 

Both the westbound and eastbound carriageways will be affected.

Here is a list of the disruptions that will affect late night drivers.

April

22-26 April - Westbound overnight full closures (from 20:00 to 06:00)

27-29 April - Westbound full weekend closure (from 21:00 on Saturday to 06:00 on Monday)

29-30 April - Westbound overnight full closures

May

1-16 May - Westbound overnight full closures

17-20 May - Westbound full weekend closure (from 21:00 on Saturday to 06:00 on Monday)

20-23 May - Westbound overnight full closures

28-31 May - Westbound overnight full closures

June

3-7 June - Westbound overnight full closures

14-17 June - Eastbound full weekend closure (from 21:00 on Saturday to 06:00 on Monday)

17-20 June - Eastbound overnight full closures

21-24 June - Eastbound full weekend closure (from 21:00 on Saturday to 06:00 on Monday)

24-27 June - Eastbound overnight full closures

28-1 July - Westbound full weekend closure (from 21:00 on Saturday to 06:00 on Monday)

July

1- 4 July - Westbound overnight full closures

5-8 July - Eastbound full weekend closure (from 21:00 on Saturday to 06:00 on Monday)

8-11 July - Eastbound overnight full closures

12-15 July - Westbound full weekend closure (from 21:00 on Saturday to 06:00 on Monday - contingency)

15-18 July - Westbound overnight full closures (contingency)

19-22 July - Eastbound full weekend closure (from 21:00 on Saturday to 06:00 on Monday - contingency)

22-25 July - Eastbound overnight full closures (Contingency)